May 2007
Most of this months page is dedicated to a small gang of
workers that has toiled away quietly, week in - week
out, on a vital aspect of the waterfront development;
the wave wall. The expanded image left, taken May 2nd,
reveals there's just a few days of the staggered
pouring sequence remaining.
They've been hard at it since October last year; 7 1/2
months of form, pour, strip, clean, then form up again!
May 8th, this is the day they've been waiting for, all
ready for the last main pour on the 650m long wall.
|