The image left, is an aerial photo from the NT Government's web site
about the Waterfront Development. Look closely at the earthworks on the
left hand end of the seawall in the expanded image, and you will see that
they are almost complete. A check back to a similar image on the May 2006 page
will show you just how much progess has been made, particularly on the Convention
Centre.
Construction of the wavewall is now underway using purpose built steel forms
to enable a rapid casting sequence. The concrete wall sits atop a cast insitu
footing and raises the seawall to it's final height. There is a lip on the
outside of the wall to turn any cresting waves back on themselves. A promenade
will be constructed on the inside so people can eventually stroll the full
length of the wall.
|